//Construction of Tabriz – Ahar highway, lot 3
Construction of Tabriz – Ahar highway, lot 32020-01-18T13:15:20+03:30

Project Description

Construction of Tabriz – Ahar highway, lot 3

  • Project: Construction of Tabriz – Ahar highway, lot 3
  • Client: Roads and Urban Development Administration, East Azarbayejan
  • Contract Amount: USD 7.1 million

  • Start date: April 2015

  • Duration: 12 months

  • Progress: 69%

Location

  • Tabriz – Ahar, Iran

Scope of work

  • Roads and Urban Development Administration, East Azarbayejan
  • Construction of Tabriz – Ahar highway, lot 3

Main Figures

  • Excavation: 1,870,000 m³
  • Explosion: 225,000 m³
  • Embankment: 1,410,000 m³
  • Sub-base: 92,000 m³
  • Base: 80,000 m³
  • Asphalt: 248,000 tons
  • Formwork: 130,000 m2
  • Rebar: 1500 ton
  • Concrete pouring: 41,000 m³
  • Guardrail works: 40 km
  • Lining: 21 km long, 4 lanes
  • Bridges: 169; 14 spanning over 10 meters