//Construction of the control tower, technical block, fire-fighting building, and the apron; Persian Gulf International Airport, Assaluye
Construction of the control tower, technical block, fire-fighting building, and the apron; Persian Gulf International Airport, Assaluye2020-01-18T13:55:25+03:30

Project Description

Construction of the control tower, technical block, fire-fighting building, and the apron; Persian Gulf International Airport, Assaluye

  • Project: Construction of the control tower, technical block, fire-fighting building, and the apron; Persian Gulf International Airport, Assaluye

  • Client: Pars Special Economic Energy Zone

  • Contract Amount: USD 9.2 million

  • Actual Amount: USD 11.4 million

  • Start date: May 2004

  • End date: December 2005

  • Duration: 9 months

Project Description