//Phases 6, 7, and 8 South Pars Gas
Phases 6, 7, and 8 South Pars Gas2020-01-18T13:17:31+03:30

Project Description

Civil works (C4A, Unit 102 & 109) and Building Works (C4B –Packages 1 & 2) – Phases 6, 7, and 8 – Onshore facilities

  • Project: Civil works (C4A, Unit 102 & 109) and Building Works (C4B – Packages 1 & 2) – Phases 6, 7, and 8 – Onshore facilities
  • Client: Toyo Engineering Corporation

  • Contract Amount: USD 30.0 million

  • Actual Amount: USD 30.0 million

  • Duration: 24 months

  • Start date: January 2004

  • End date: June 2007

Location

  • Assaluye, Iran

Scope of work

  • Phases C4A and C4B
  • Construction of pipe racks
  • U/G piping
  • Industrial Buildings: Sub-station, Control room, Fire Fighting Building, etc.
  • Camp Area: Field office, warehouse, tool store, workshop, fabrication and maintenance shops, storage facilities, etc.

Main Figures

  • Excavation in rock terrain: 230,000 m³
  • Concrete Pouring: 60,000 m³
  • Reinforcement: 6600 tons
  • Formwork: 160,000 m²
  • Camp Area and Industrial Buildings: 9,000 m²

Achievements

  • Safety award, presented by TIJD JV, for Navrood’s high safety standards, and for surpassing 15,000,000 man-hours without a lost-time incident.

Comments

  • A steady communication link and data stream was put in place all through the project management organization, and a successful quality management system was set up. A well-organized and resourced HSE unit, as well as an effective cost control procedure was devised to ensure on time and on budget completion of the project.