//Procurement and construction of non-industrial buildings, phases 22, 23, and 24, South Pars Gas Field Development Project
Procurement and construction of non-industrial buildings, phases 22, 23, and 24, South Pars Gas Field Development Project2020-01-18T13:25:27+03:30

Project Description

Procurement and construction of non-industrial buildings, phases 22, 23, and 24, South Pars Gas Field Development Project

  • Project: Procurement and construction of non-industrial buildings, phases 22, 23, and 24, South Pars Gas Field Development Project

  • Client: Petro Sina Oil & Gas Co.

  • Contract Amount: USD 18.4 million

  • Actual Amount: USD 18.4 million

  • Start date: February 2011

  • End date: December 2015

  • Duration: 18 months