1 P.E.E.S.Z
Construction of internal streets in P.E.E.S.Z one
34
36
2007
OnTime
2 N.I.O.C
Civil work’s Gas development, Refinery, phase 6, 7 & 8 C4-B package 1,2 Assaluye- Iran
5.9
18
2007
OnTime
3 N.I.O.C Civil Work Gas Develpment,Refinery,Phase 6,7,8 C4-A Package Assaluyeh
10.54
20
2007
OnTime
4 P.E.E.S.Z Completion Operation Of Assaluyeh International Airport
6.5
9
2006
OnTime
5 P.E.E.S.Z Assaluyeh Construction International Airport
8.3
27
2004
OnTime
6 ASPC Ethane cracking plant, 9th olephin (N.S.T) J.V(Navrood, Steam & T.E.G)
43.8
39
2002
OnTime
7 P.E.E.S.Z Construction of highway in P.E.E.S.Z Belt Lot 3
7.8
42
2001
OnTime
8 Iran National Gas Company
Pipe laying Project (50 km, Bane-Sardasht)
14
24
2001
OnTime
9 Iran National Gas Company
48" Dia. Pipe laying Project (170 km, Miane-Tabriz)
28
36
1999
OnTime
10 Tabriz Petrochemical Company
Construction of Laboratory Building (N.D.T)
1.4
6
June 19, 1997
OnTime
11 Ministry of Road and Transportation
Khosroshahr- Islamic Island Main Road
5.5
22.5
September 3, 1996
OnTime
12 Ministry of Road and Transportation construction of Ahar-Tabriz Main Road Lot 4
15
30
September 3, 1996
OnTime
13 Ministry of Road and Transportation
Extension of Hamedan-Rowan Main Road to Highway
6
22.5
March 14, 1995
OnTime
14 Tabriz Petrochemical Company
General Workshop
1.7
6
October 17, 1995
OnTime
15 Ministry of Road and Transportation
Tabriz By Pass Freeway
8.5
18
March 19, 1994
OnTime
16 Tabriz Petrochemical Company Civil & U/G Piping Raw/Portable/D/M Water Plant
5.6
10
August 10, 1994
OnTime
17 Tabriz Petrochemical Company Construction of Buildings for Offsite Areas
2.5
6
September 19, 1994
OnTime
18 Ministry of Road and Transportation
Saveh-Hamedan Asphalt (Main Road)
12
36
July 2, 1993
OnTime
19 Tabriz Petrochemical Company Civil & U/G Piping Works, Off sites
19
20
December 15, 1993
OnTime
20 Tabriz Petrochemical Company Site Grading and Construction of Roads
 
5
8
June 20, 1991
OnTime
21 Tabriz Petrochemical Company
Fencing & Patrol Roads
1.2
10
April 14, 1990
OnTime
22 Ministry of Road and Transportation
Avaj-Hamedan Main Road
21
90
June 25, 1990
OnTime
23
PipeLaying of Uromiyeh 30'' Gas Pipe line
PipeLaying of Uromiyeh 30'' Gas Pipe line
17 20 2009 OnTime
24 Construction Of Interchange of Jam-Taheri Highway Construction Of Interchange of Jam-Taheri Highway 3.5 12 2008 OnTime
25 Paivement Phase 9 & 10 Paivement Phase 9&10 7.2 8 2008 OnTime
26 Construction of Protection Dyke - Package 5 (P5E1) Construction of Protection Dyke - Package 5 (P5E1) 8.0 8 2008 OnTime

 

 